CITY OF LAKEFIELD: Construction update #22

Contructions

City Of Lakefield issued the following announcement on May 13.

Construction update #22

Week of May 9, 2022

The contractor continued to place sanitary sewer main on TH86 going south from the Funk Avenue intersection toward the 7th Avenue intersection. New Sanitary sewer main has currently been placed up to the 7th Avenue intersection. Storm Sewer placement has been installed from the river on the north end of town to approximately the center of the Wastewater Treatment Facility. This week we had a rain event on Wednesday night that halted construction until the site has been cleaned up and bypass pumping has been caught up. Concrete sidewalk has begun on Chicago Street and Is approximately 50% complete. Summer Lane driveways have been poured and currently the street is now ready for milling and paving.

Week of May 16, 2022

The contractor will continue with sanitary sewer and storm sewer installation on TH86 with progress going south to Menage Avenue. If the contractor can reach the Menage Avenue intersection he will then possibly begin water main installation between the Wastewater Treatment Plant and Menage Avenue. The concrete contractor will be back on site next week and intends to finish the sidewalk installation on Chicago Street.

General Information

Garbage and Recycling bins are currently being relocated by the contractor for pick up in affected areas. If your bins have not been marked indicating your house number, please do so and try to maintain the number on your bins if possible as it is easy to mix up garbage bins. As a reminder, TH86 is currently closed for north and south traffic; however, TH86 crossings between Mill Road and Menage Avenue are open. There are several residences and businesses on TH86 and as a friendly reminder please remember to take the most direct route to avoid TH86 as there is much concern for safety during construction.

If you are interested in receiving future Project Updates by email, please send your name, property address, and email address to Julie Brinkman at jbrinkman@sehinc.com.

If you have any questions or concerns, feel free to contact me or Project Manager Brent Kavitz.

Joel Bartscher, Resident Project Representative

605.933.0790

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS